We do something very similar at my work, except we dont use index cards (in part because my handwriting is atrocious (damn that Palm graphitti!) and because I type much faster than I could ever possibly write).

When we have to estimate a task, we start out with a list of the functionality the client wants. Then we break it down into the tasks we need to take to accomplish that functionality. Then we begin estimating how long things will take.

We then have a few general rules we follow.

  • Murphy's Law is always taken into account (for those who don't know, "anything that can go wrong, will go wrong")
    No matter what, it is better to estimate for the worst case scenario, then the best case. You can even tell the client this if you want. I find telling this to the client is useful in illustrating how important it is that they meet their deliverables ("it will take a week if you get us the data on time, or two weeks otherwise", etc. etc.)
  • Testing, testing, testing.
    Our general rule of thumb is x1.5-2 for testing. This includes unit testing, integration testing and final acceptence testing.

    We use to just double our estimates to allow for problems/bugs/issues. But the more we adopted TDD, the more we realized that if that time went to writing tests, then the likelihood of those problems/bugs/issues was reduced and overall quality was higher. This also can be brownie points with certain clients, they like to hear you are properly planning time for testing rather then just leaving it till the end (which basically means it won't get tested).

  • System administration time.
    As a programmer, I never would think about the sys-admin time to accomplish a certain task, because I never saw it as "part of the task". This actually goes for all tasks which you in particular are not responsible for. It helps to know the bigger picture basically.

Once the estimate goes off to the client it is out of your hands. However, this does not mean that everything is written in stone. Proper handling of scope creep is critical. I used to be hesitant and uncomfortable when dealing with clients on scope creep. But I have realized over the years that you get more respect from a client, and get taken advantage of less if you are hard and fast about scope creep. If explained properly, your client will understand and agree, and you can negotiate. If a client is too pushy and want's you to do it for free, then they are clearly trying to take advantage of you, and you need to respond appropriately. Always remember, your clients are not your friends. That is not to say that a particular contact at a client might not become your friend (I have worked with one guy for 3 years now and we are good friends), but when dealing with matters of business, friendship and feelings need to be left at the conference room door.

Another thing I have found is very helpful, is to make sure that client deliverables are on the schedule and those dates are enforced. Many times my estimate has been derailed because they were late, however since compliance was not enforced, my schedule was never changed, and I ended up working nights and weekends.

I say client many times here, but within reason you can substitue "account guy" or "project manager" for client (taking into account the subtleties of office politics of course).

-stvn

In reply to Re: Improving Your Ability to Estimate by stvn
in thread Improving Your Ability to Estimate by dws

Title:
Use:  <p> text here (a paragraph) </p>
and:  <code> code here </code>
to format your post; it's "PerlMonks-approved HTML":



  • Are you posting in the right place? Check out Where do I post X? to know for sure.
  • Posts may use any of the Perl Monks Approved HTML tags. Currently these include the following:
    <code> <a> <b> <big> <blockquote> <br /> <dd> <dl> <dt> <em> <font> <h1> <h2> <h3> <h4> <h5> <h6> <hr /> <i> <li> <nbsp> <ol> <p> <small> <strike> <strong> <sub> <sup> <table> <td> <th> <tr> <tt> <u> <ul>
  • Snippets of code should be wrapped in <code> tags not <pre> tags. In fact, <pre> tags should generally be avoided. If they must be used, extreme care should be taken to ensure that their contents do not have long lines (<70 chars), in order to prevent horizontal scrolling (and possible janitor intervention).
  • Want more info? How to link or How to display code and escape characters are good places to start.
Log In?
Username:
Password:

What's my password?
Create A New User
Domain Nodelet?
Chatterbox?
and the web crawler heard nothing...

How do I use this?Last hourOther CB clients
Other Users?
Others drinking their drinks and smoking their pipes about the Monastery: (4)
As of 2024-04-23 16:28 GMT
Sections?
Information?
Find Nodes?
Leftovers?
    Voting Booth?

    No recent polls found